PPT Slide
MuTr FEE System Test--Cost
Cost of octant test boards:
- If boards need changes, the boards used for octant test would not be re-usable
- Even if no changes required, fast turn-around will mean increased price
Extra setup costs for octant test
Engineers required on payroll for longer time
Total cost increase for FEE ~ 70k
Longer delay before contingency money is freed up for North Arm Mechanics--> increased cost for mechanics