- Sufficient contingency funds should be created to assure South arm completion before major financial commitments are made to the North arm
- A large-scale system test of the Muon Tracker electronics should be carried out before release for fabrication of the full complement of electronics boards
- Results of test should be reviewed prior to production
- The complete grounding and shielding plan for the muon tracking detector readout should be documented and submitted to a detailed review by PHENIX electronics management
- Recommend that PHENIX, RHIC and LANL management work together to assure engineering support throughout MuTr FEE testing
- MuID FEE should increase time allotted to fabrication and production to give schedule contingency