FEE Production Task Times
Test CPA Chips (4000) 5 man-weeks
Assemble Chassis (50, 50) 7/day (can be less)
Fill (help assemble?) Racks 4 weeks
*Order Boards (Backplane, CROC, Ctlr, Glink/Clink) 12 weeks
Put Backplanes on Chassis 10/day
Initial Board Test (Pass/Fail) 10-15 minutes/board
Assemble Glink/Clink Crates (10) 1 week
Fill Chassis with Boards (100) 5/day
Ming, Andrew, LANL staff and BNL instrumentation:
Debug Failed Boards 4 weeks/board type(short?)
Put Chassis on CRA and test 1 CRA/3.75 days
Hook up CRAs, Station 1 Chassis to Racks 1 CRA/3.75 days
Assembly Hall - BNL Techs
Assemble and Install Eyebrow 6 weeks
Install In-magnet framework 1 week
Install Station 1 FEE Plate 1 week
Install CRAs, Station 1 Chassis? 1 CRA/3.75 days