Students (2): When How Long?
Test CPA Chips Jan-Feb 5 wk
Assemble Chassis (50, 50) Jan, May 3 wk
Fill (help assemble?) Racks March 4 wk
*Order Boards (Backplane, CROC, Ctlr, Glink/Clink)* March-May 12 wk
Put Backplanes on Chassis May 2 wk
Initial Board Test (Pass/Fail) May-beg.June 4 wk
Assemble Glink/Clink Crates (10) June 1 wk
Fill Chassis with Boards(100) June-July 4 wk
Ming, Andrew, LANL Staff and BNL Instrumentation:
Set up Burn-in facility for boards April
Debug Failed Boards June 8 wk
Put Chassis on CRA and test June-Sept. 12 wk
Hook up CRAs, Station 1 Chassis to Racks June-Sept. 12, 6 wk
Assembly Hall - BNL Techs
Assemble and Install Eyebrow April ə wk
Install In-magnet framework May 1 wk
Install Station 1 FEE Plate May? 1 wk
Install CRAs, Station 1 Chassis? June-Sept. 12 wk