| ID | Task Name | Duration | Start | Finish | Resource Names | % Complete |
| 1 | Finish North side | 145.75 days | Fri 3/15/02 | Fri 10/4/02 | | 65% |
| 2 | Sector EON | 132.5 days | Fri 3/15/02 | Tue 9/17/02 | | 39% |
| 3 | Disassemble Sector | 125.5 days | Fri 3/15/02 | Fri 9/6/02 | | 100% |
| 4 | Remove electronics | 0.8 days | Fri 3/15/02 | Fri 3/15/02 | | 100% |
| 5 | Remove P/s Boards | 0.5 days | Fri 3/15/02 | Fri 3/15/02 | Rob,Carter | 100% |
| 6 | Remove signal cables | 0.1 days | Fri 3/15/02 | Fri 3/15/02 | Rob,Carter | 100% |
| 7 | Remove LV cables | 0.05 days | Fri 3/15/02 | Fri 3/15/02 | Rob,Carter | 100% |
| 8 | Remove HV cables | 0.05 days | Fri 3/15/02 | Fri 3/15/02 | Rob,Carter | 100% |
| 9 | Move Gas manifold | 0.3 days | Tue 3/19/02 | Tue 3/19/02 | Carter | 100% |
| 10 | remove cable trays | 0.5 days | Wed 3/20/02 | Wed 3/20/02 | Rob,Xinhua | 100% |
| 11 | strip down tray | 0.3 days | Wed 3/20/02 | Wed 3/20/02 | Mark,Achim,Xinhua | 100% |
| 12 | Remove TRD ground straps | 0.5 days | Wed 3/20/02 | Wed 3/20/02 | Rob | 100% |
| 13 | open TR door | 0.5 days | Fri 9/6/02 | Fri 9/6/02 | Rob | 100% |
| 14 | Assemble Sector EON | 7 days | Fri 9/6/02 | Tue 9/17/02 | | 14% |
| 15 | insert TR | 1 day | Fri 9/6/02 | Mon 9/9/02 | Rob | 100% |
| 16 | HV test chambers | 0.25 days | Mon 9/9/02 | Mon 9/9/02 | | 0% |
| 17 | seal Doors | 0.5 days | Mon 9/9/02 | Tue 9/10/02 | | 0% |
| 18 | Attach TRD ground straps | 0.5 days | Tue 9/10/02 | Tue 9/10/02 | | 0% |
| 19 | Attach gas TRD manifold | 1 day | Tue 9/10/02 | Wed 9/11/02 | | 0% |
| 20 | attach cable tray | 1 day | Wed 9/11/02 | Thu 9/12/02 | | 0% |
| 21 | attach stand offs and align | 0.25 days | Thu 9/12/02 | Thu 9/12/02 | | 0% |
| 22 | attach gas manifold | 0.5 days | Fri 9/13/02 | Fri 9/13/02 | | 0% |
| 23 | run cables | 1 day | Fri 9/13/02 | Mon 9/16/02 | | 0% |
| 24 | replace electronics | 1 day | Mon 9/16/02 | Tue 9/17/02 | | 0% |
| 25 | | | | | | |
| 26 | Sector E1N | 131.75 days | Thu 4/4/02 | Fri 10/4/02 | | 73% |
| 27 | Disassemble certor | 113 days | Thu 4/4/02 | Mon 9/9/02 | | 100% |
| 28 | Remove electronics | 55.1 days | Thu 4/4/02 | Thu 6/20/02 | | 100% |
| 29 | Remove P/s Boards | 0.5 days | Thu 4/4/02 | Thu 4/4/02 | Mark,Xinhua | 100% |
| 30 | Remove signal cables | 0.1 days | Thu 6/20/02 | Thu 6/20/02 | Rob | 100% |
| 31 | Remove LV cables | 0.05 days | Thu 6/20/02 | Thu 6/20/02 | Rob | 100% |
| 32 | Remove HV cables | 0.05 days | Thu 6/20/02 | Thu 6/20/02 | Rob | 100% |
| 33 | Move Gas manifold | 0.3 days | Thu 6/20/02 | Thu 6/20/02 | Rob | 100% |
| 34 | remove cable trays | 0.5 days | Fri 6/21/02 | Fri 6/21/02 | Rob | 100% |
| 35 | Strip down tray | 0.3 days | Fri 6/21/02 | Fri 6/21/02 | Rob | 100% |
| 36 | Remove TRD ground straps | 0.5 days | Mon 9/9/02 | Mon 9/9/02 | Rob | 100% |
| 37 | open TR door | 0.5 days | Mon 9/9/02 | Mon 9/9/02 | Rob | 100% |
| 38 | Assemble Sector E1N | 18.75 days | Tue 9/10/02 | Fri 10/4/02 | | 64% |
| 39 | insert TR | 2 days | Tue 9/10/02 | Wed 9/11/02 | Rob | 100% |
| 40 | HV test chambers | 0.25 days | Thu 9/12/02 | Thu 9/12/02 | Rob | 100% |
| 41 | seal Doors | 1 day | Thu 9/12/02 | Fri 9/13/02 | Carter | 100% |
| 42 | Attach ground straps | 0.5 days | Mon 9/16/02 | Mon 9/16/02 | Rob | 100% |
| 43 | Attach gas TRD manifold | 0.5 days | Mon 9/16/02 | Tue 9/17/02 | Rob,Achim | 0% |
| 44 | attach cable tray | 1.5 days | Tue 9/17/02 | Tue 10/1/02 | John,bill | 100% |
| 45 | attach stand offs and align | 0.25 days | Wed 10/2/02 | Wed 10/2/02 | John,bill | 80% |
| 46 | attach gas manifold | 0.5 days | Wed 10/2/02 | Wed 10/2/02 | | 0% |
| 47 | run cables | 1 day | Wed 10/2/02 | Thu 10/3/02 | | 0% |
| 48 | replace electronics | 1 day | Thu 10/3/02 | Fri 10/4/02 | | 0% |
| 49 | | | | | | |
| 50 | Sector E2N | 24.25 days | Mon 4/29/02 | Fri 5/31/02 | | 72% |
| 51 | Disassemble Sector | 15 days | Mon 4/29/02 | Fri 5/17/02 | | 100% |
| 52 | Remove electronics | 0.5 days | Mon 4/29/02 | Mon 4/29/02 | | 100% |
| 53 | Remove P/s Boards | 0.5 days | Mon 4/29/02 | Mon 4/29/02 | Rob | 100% |
| 54 | Remove signal cables | 0.1 days | Mon 4/29/02 | Mon 4/29/02 | Rob | 100% |
| 55 | Remove LV cables | 0.05 days | Mon 4/29/02 | Mon 4/29/02 | Rob | 100% |
| 56 | Remove HV cables | 0.05 days | Mon 4/29/02 | Mon 4/29/02 | Rob | 100% |
| 57 | Move Gas manifold | 0.3 days | Mon 4/29/02 | Mon 4/29/02 | Rob | 100% |
| 58 | remove cable trays | 0.5 days | Mon 4/29/02 | Mon 4/29/02 | Rob,Carter | 100% |
| 59 | strip down tray | 0.3 days | Mon 4/29/02 | Tue 4/30/02 | Rob | 100% |
| 60 | Remove ground straps | 0.5 days | Tue 4/30/02 | Tue 4/30/02 | Rob | 100% |
| 61 | open TR door | 0.5 days | Fri 5/17/02 | Fri 5/17/02 | Rob,Carter | 100% |
| 62 | Assemble Sector E2N | 9.25 days | Mon 5/20/02 | Fri 5/31/02 | | 63% |
| 63 | insert TR | 2 days | Mon 5/20/02 | Tue 5/21/02 | Carter,Rob | 100% |
| 64 | HV test chambers | 0.25 days | Wed 5/22/02 | Wed 5/22/02 | Rob | 100% |
| 65 | seal Doors | 1 day | Thu 5/23/02 | Thu 5/23/02 | Carter,Rob | 100% |
| 66 | Attach ground straps | 0.5 days | Fri 5/24/02 | Fri 5/24/02 | Rob | 100% |
| 67 | Attach gas TRD manifold | 1.17 days | Fri 5/24/02 | Mon 5/27/02 | Carter,Rob,Achim | 43% |
| 68 | attach cable tray | 1 day | Mon 5/27/02 | Tue 5/28/02 | bill,John | 100% |
| 69 | attach stand offs and align | 0.25 days | Tue 5/28/02 | Tue 5/28/02 | John,bill | 85% |
| 70 | attach gas manifold | 0.5 days | Tue 5/28/02 | Wed 5/29/02 | | 0% |
| 71 | run cables | 1 day | Wed 5/29/02 | Thu 5/30/02 | | 0% |
| 72 | replace electronics | 1 day | Thu 5/30/02 | Fri 5/31/02 | | 0% |
| 73 | | | | | | |
| 74 | Sector E3N | 107.5 days | Fri 4/26/02 | Tue 9/24/02 | | 74% |
| 75 | Disassemble Sector | 98 days | Fri 4/26/02 | Tue 9/10/02 | | 100% |
| 76 | Remove electronics | 0.5 days | Fri 4/26/02 | Fri 4/26/02 | Carter | 100% |
| 77 | Remove P/s Boards | 0.5 days | Fri 4/26/02 | Fri 4/26/02 | Carter | 100% |
| 78 | Remove signal cables | 0.1 days | Fri 4/26/02 | Fri 4/26/02 | Carter | 100% |
| 79 | Remove LV cables | 0.05 days | Fri 4/26/02 | Fri 4/26/02 | Carter | 100% |
| 80 | Remove HV cables | 0.05 days | Fri 4/26/02 | Fri 4/26/02 | Carter | 100% |
| 81 | Move Gas manifold | 0.3 days | Fri 4/26/02 | Fri 4/26/02 | Carter | 100% |
| 82 | remove cable trays | 0.5 days | Mon 4/29/02 | Mon 4/29/02 | Carter | 100% |
| 83 | strip down tray | 0.3 days | Mon 4/29/02 | Mon 4/29/02 | Rob | 100% |
| 84 | Remove ground straps | 0.5 days | Tue 9/10/02 | Tue 9/10/02 | Rob,Carter | 100% |
| 85 | open TR door | 0.5 days | Tue 9/10/02 | Tue 9/10/02 | Rob,Carter | 100% |
| 86 | Assemble Sector E3N | 9.5 days | Wed 9/11/02 | Tue 9/24/02 | | 66% |
| 87 | insert TR | 2 days | Wed 9/11/02 | Thu 9/12/02 | Rob,Carter | 100% |
| 88 | HV test chambers | 0.2 days | Fri 9/13/02 | Fri 9/13/02 | Rob | 100% |
| 89 | seal Doors | 1 day | Mon 9/16/02 | Mon 9/16/02 | Carter | 100% |
| 90 | Attach ground straps | 0.5 days | Tue 9/17/02 | Tue 9/17/02 | Rob | 100% |
| 91 | Attach gas TRD manifold | 1 day | Tue 9/17/02 | Wed 9/18/02 | Carter,Rob | 50% |
| 92 | attach cable tray | 1 day | Wed 9/18/02 | Thu 9/19/02 | Rob,John | 100% |
| 93 | attach stand offs and align | 0.5 days | Thu 9/19/02 | Thu 9/19/02 | John,Rob | 100% |
| 94 | attach gas manifold | 0.5 days | Fri 9/20/02 | Fri 9/20/02 | | 0% |
| 95 | run cables | 1 day | Fri 9/20/02 | Mon 9/23/02 | | 0% |
| 96 | replace electronics | 1 day | Mon 9/23/02 | Tue 9/24/02 | | 0% |
| 97 | | | | | | |
| 98 | Finish Sorth side | 127 days | Mon 3/18/02 | Tue 9/10/02 | | 76% |
| 99 | Sector EOS | 65.5 days | Mon 3/18/02 | Mon 6/17/02 | | 70% |
| 100 | Disassemble Sector | 56 days | Mon 3/18/02 | Mon 6/3/02 | | 100% |
| 101 | Remove electronics | 0.5 days | Mon 3/18/02 | Mon 3/18/02 | | 100% |
| 102 | Remove P/s Boards | 0.5 days | Mon 3/18/02 | Mon 3/18/02 | Basanta,Xinhua | 100% |
| 103 | Remove signal cables | 0.1 days | Mon 3/18/02 | Mon 3/18/02 | Rob | 100% |
| 104 | Remove LV cables | 0.05 days | Mon 3/18/02 | Mon 3/18/02 | Rob | 100% |
| 105 | Remove HV cables | 0.05 days | Mon 3/18/02 | Mon 3/18/02 | Rob | 100% |
| 106 | Move Gas manifold | 0.3 days | Fri 3/22/02 | Fri 3/22/02 | Carter | 100% |
| 107 | remove cable trays | 0.5 days | Tue 4/9/02 | Tue 4/9/02 | Rob | 100% |
| 108 | strip down tray | 0.3 days | Fri 4/19/02 | Fri 4/19/02 | Rob | 100% |
| 109 | Remove TRD ground straps | 0.5 days | Mon 6/3/02 | Mon 6/3/02 | Rob | 100% |
| 110 | open TR door | 0.5 days | Mon 6/3/02 | Mon 6/3/02 | Rob,Carter | 100% |
| 111 | Assemble Sector EOS | 9.5 days | Tue 6/4/02 | Mon 6/17/02 | | 60% |
| 112 | attach cable tray | 1 day | Tue 6/4/02 | Tue 6/4/02 | | 100% |
| 113 | insert TR | 2 days | Wed 6/5/02 | Thu 6/6/02 | oliver,Carter | 100% |
| 114 | HV test chambers | 0.25 days | Fri 6/7/02 | Fri 6/7/02 | Rob | 100% |
| 115 | seal Doors | 1 day | Mon 6/10/02 | Mon 6/10/02 | Carter | 100% |
| 116 | Attach ground straps | 0.5 days | Tue 6/11/02 | Tue 6/11/02 | Rob | 100% |
| 117 | Attach gas TRD manifold | 1 day | Tue 6/11/02 | Wed 6/12/02 | Rob,Carter | 50% |
| 118 | attach stand offs and align | 0.5 days | Wed 6/12/02 | Wed 6/12/02 | | 0% |
| 119 | attach gas manifold | 0.5 days | Thu 6/13/02 | Thu 6/13/02 | | 0% |
| 120 | run cables | 1 day | Thu 6/13/02 | Fri 6/14/02 | | 0% |
| 121 | replace electronics | 1 day | Fri 6/14/02 | Mon 6/17/02 | | 0% |
| 122 | | | | | | |
| 123 | Sector E1S | 59.5 days | Thu 3/28/02 | Wed 6/19/02 | | 82% |
| 124 | Disassemble Sector | 52 days | Thu 3/28/02 | Fri 6/7/02 | | 100% |
| 125 | Remove electronics | 30.1 days | Thu 3/28/02 | Thu 5/9/02 | | 100% |
| 126 | Remove P/s Boards | 0.5 days | Thu 3/28/02 | Thu 3/28/02 | Mark,Xinhua | 100% |
| 127 | Remove signal cables | 0.1 days | Thu 3/28/02 | Thu 3/28/02 | Rob | 100% |
| 128 | Remove LV cables | 0.05 days | Thu 5/9/02 | Thu 5/9/02 | Rob | 100% |
| 129 | Remove HV cables | 0.05 days | Thu 5/9/02 | Thu 5/9/02 | Rob | 100% |
| 130 | Move Gas manifold | 0.3 days | Thu 5/9/02 | Thu 5/9/02 | Carter | 100% |
| 131 | remove cable trays | 0.5 days | Thu 5/9/02 | Thu 5/9/02 | Carter,Rob | 100% |
| 132 | strip down tray | 0.3 days | Thu 5/9/02 | Thu 5/9/02 | Rob | 100% |
| 133 | Remove ground straps | 0.5 days | Fri 6/7/02 | Fri 6/7/02 | Rob | 100% |
| 134 | open TR door | 0.5 days | Fri 6/7/02 | Fri 6/7/02 | Carter,Rob | 100% |
| 135 | Assemble Sector E1S | 7.5 days | Mon 6/10/02 | Wed 6/19/02 | | 76% |
| 136 | insert TR | 2 days | Mon 6/10/02 | Tue 6/11/02 | Carter,oliver | 100% |
| 137 | HV test chambers | 0.25 days | Mon 6/10/02 | Mon 6/10/02 | Rob | 100% |
| 138 | seal Doors | 1 day | Tue 6/11/02 | Tue 6/11/02 | Carter | 100% |
| 139 | Attach ground straps | 0.5 days | Wed 6/12/02 | Wed 6/12/02 | Rob | 100% |
| 140 | Attach gas TRD manifold | 1 day | Wed 6/12/02 | Thu 6/13/02 | Rob,oliver,Carter | 100% |
| 141 | attach cable tray | 1 day | Thu 6/13/02 | Fri 6/14/02 | John,Carter | 100% |
| 142 | attach stand offs and align | 0.5 days | Fri 6/14/02 | Fri 6/14/02 | Carter,Rob | 100% |
| 143 | attach gas manifold | 0.5 days | Mon 6/17/02 | Mon 6/17/02 | Carter | 80% |
| 144 | run cables | 1 day | Mon 6/17/02 | Tue 6/18/02 | | 0% |
| 145 | replace electronics | 1 day | Tue 6/18/02 | Wed 6/19/02 | | 0% |
| 146 | | | | | | |
| 147 | Sector E2S | 61.83 days | Wed 3/27/02 | Thu 6/20/02 | | 70% |
| 148 | Disassemble Sector | 53 days | Wed 3/27/02 | Fri 6/7/02 | | 100% |
| 149 | Remove electronics | 1 day | Wed 3/27/02 | Wed 3/27/02 | Carter,Rob | 100% |
| 150 | Remove P/s Boards | 1 day | Wed 3/27/02 | Wed 3/27/02 | Carter,Rob | 100% |
| 151 | Remove signal cables | 1 day | Wed 3/27/02 | Wed 3/27/02 | Carter,Rob | 100% |
| 152 | Remove LV cables | 1 day | Wed 3/27/02 | Wed 3/27/02 | Carter,Rob | 100% |
| 153 | Remove HV cables | 1 day | Wed 3/27/02 | Wed 3/27/02 | Carter,Rob | 100% |
| 154 | Move Gas manifold | 0.3 days | Thu 4/4/02 | Thu 4/4/02 | Carter,Rob | 100% |
| 155 | remove cable trays | 0.5 days | Thu 4/4/02 | Thu 4/4/02 | Carter,Rob | 100% |
| 156 | strip down tray | 0.3 days | Thu 4/4/02 | Fri 4/5/02 | Rob | 100% |
| 157 | Remove ground straps | 0.5 days | Fri 6/7/02 | Fri 6/7/02 | Rob | 100% |
| 158 | open TR door | 0.5 days | Fri 6/7/02 | Fri 6/7/02 | Carter | 100% |
| 159 | Assemble Sector E2S | 8.83 days | Mon 6/10/02 | Thu 6/20/02 | | 47% |
| 160 | insert TR | 1.33 days | Mon 6/10/02 | Tue 6/11/02 | Rob,Carter,oliver | 100% |
| 161 | HV test chambers | 0.25 days | Tue 6/11/02 | Tue 6/11/02 | Rob | 100% |
| 162 | seal Doors | 1 day | Wed 6/12/02 | Thu 6/13/02 | Rob | 80% |
| 163 | Attach ground straps | 0.5 days | Thu 6/13/02 | Thu 6/13/02 | Rob | 80% |
| 164 | Attach gas TRD manifold | 1 day | Thu 6/13/02 | Fri 6/14/02 | Rob,Carter | 50% |
| 165 | attach cable tray | 1 day | Fri 6/14/02 | Mon 6/17/02 | | 0% |
| 166 | attach stand offs and align | 0.5 days | Mon 6/17/02 | Tue 6/18/02 | | 0% |
| 167 | attach gas manifold | 0.5 days | Tue 6/18/02 | Tue 6/18/02 | | 0% |
| 168 | run cables | 1 day | Tue 6/18/02 | Wed 6/19/02 | Rob,bill | 50% |
| 169 | replace electronics | 1 day | Wed 6/19/02 | Thu 6/20/02 | | 0% |
| 170 | | | | | | |
| 171 | Sector E3S | 127 days | Mon 3/18/02 | Tue 9/10/02 | | 83% |
| 172 | Disassemble Sector | 17.85 days | Mon 3/18/02 | Wed 4/10/02 | | 100% |
| 173 | Remove electronics | 0.7 days | Mon 3/18/02 | Mon 3/18/02 | Rob,Carter | 100% |
| 174 | Remove P/s Boards | 0.5 days | Mon 3/18/02 | Mon 3/18/02 | Rob,Carter | 100% |
| 175 | Remove signal cables | 0.1 days | Mon 3/18/02 | Mon 3/18/02 | Rob,Carter | 100% |
| 176 | Remove LV cables | 0.05 days | Mon 3/18/02 | Mon 3/18/02 | Rob,Carter | 100% |
| 177 | Remove HV cables | 0.05 days | Mon 3/18/02 | Mon 3/18/02 | Rob,Carter | 100% |
| 178 | Move Gas manifold | 0.3 days | Tue 4/2/02 | Tue 4/2/02 | Carter | 100% |
| 179 | remove cable trays | 0.5 days | Tue 4/2/02 | Tue 4/2/02 | Rob,Carter | 100% |
| 180 | strip down tray | 0.3 days | Tue 4/2/02 | Tue 4/2/02 | Rob | 100% |
| 181 | Remove TRD ground straps | 0.5 days | Wed 4/10/02 | Wed 4/10/02 | Rob,Carter | 100% |
| 182 | open TR door | 0.5 days | Wed 4/10/02 | Wed 4/10/02 | Rob,Carter | 100% |
| 183 | Assemble Sector E3S | 109.15 days | Wed 4/10/02 | Tue 9/10/02 | | 77% |
| 184 | insert TR | 2 days | Wed 4/10/02 | Fri 4/12/02 | Rob,Carter | 100% |
| 185 | HV test chambers | 0.25 days | Fri 4/12/02 | Mon 4/15/02 | Rob | 100% |
| 186 | seal Doors | 1 day | Tue 8/27/02 | Tue 8/27/02 | Carter,oliver | 100% |
| 187 | Attach ground straps | 0.5 days | Thu 8/29/02 | Thu 8/29/02 | Rob,Carter | 100% |
| 188 | Attach gas TRD manifold | 0.75 days | Thu 8/29/02 | Fri 8/30/02 | oliver,Rob | 50% |
| 189 | attach cable tray | 1 day | Thu 9/5/02 | Thu 9/5/02 | Rob,Carter | 100% |
| 190 | attach stand offs and align | 0.5 days | Fri 9/6/02 | Fri 9/6/02 | Carter,Rob | 100% |
| 191 | attach gas manifold | 0.5 days | Fri 9/6/02 | Fri 9/6/02 | | 80% |
| 192 | run cables | 1 day | Mon 9/9/02 | Mon 9/9/02 | Rob,bill | 50% |
| 193 | replace electronics | 1 day | Tue 9/10/02 | Tue 9/10/02 | | 0% |
|