Memo from Yuji & Shin’ya
PISA99 preparation
- should be available by the end of this week.
- will be installed from the beginning of the next week.
- should be installed by the mid next week.
Input data/file
- should be available by the mid next week.
- should be prepared by Charlie and each PWG.
- note: Requests from PWGs should be informed to CC-J by the mid next week.
Job scripts
- are modified from those used for MDC2 by CC-J-WG.
Events
- will be generated during Nov 22 - Dec 5 (two weeks).
- assumptions and rough estimations:
- available number of CPUs = 60
- for Au-Au
- CPU time 1 ksec/event
- data size 10 MB/event
- 50k events => 10 days, 500 GB
- for p-p
- CPU time 10 sec/event
- data size 50 kB/event (after compression)
- 5M events => 10 days, 250 GB
Data transfer
- will be by magnetic tapes. (1TB = 50GB/tape x 20tapes)
- note: Temporally dosk storage at RCF is needed.