Plan and Current Status of the CC-J
1998
1999
2000
2001
2002
RBRC
(BNL)
R&D for CC-J
RIKEN
Wako
Phase 1
Phase 2
Phase 3
1/3 scale
2/3 scale
Full scale
Prototype of CPU farms
Data Duplication facility
April
April
April
April
CC-J review at BNL
(Dec. 1998)
HPSS Software/Hardware
Installation (March 1999)
(Supplementary Budget)
CC-J starts operation
at 1/3 scale
(April. 2000)
Full scale CC-J
(Mar. 2002)
CC-J
construction
CC-J front-end at BNL
April
CC-J Working Group
formed (Oct. 1998)
PHENIX Exp. at RHIC