Order full set of production parts O.K. given 5-April following FEE review
Octant test complete mid-May
Order production boards May-Aug. (may be shorter)
Install Mech. Support Structure Aug. 2
Install Platform and Racks Aug. 9
Assemble chassis, CRAs Aug-Nov
Install chassis, CRAs Aug-Nov
FEE Installation complete Nov. 10
Activities to follow FEE Installation:
- Connections to counting house, plumbing, etc.
- Installation of Magnet Buss