- Mechanical Structures:
- Chassis and cross-rib assemblies delivered to BNL some time ago. Assembly mostly complete, by Andrew, some plumbing still needs to be received.
- Board Status:
- First control board (3rd round) received (LANL) and checked out o.k.; Full order placed.
- First Readout Card (3rd round) expected this week; full order will follow
- Noise specs already achieved on large fraction of the channels; this latest version should have layout fixes required to meet specs on all channels
- Backplanes expected 17-April
- HV
- Initial hookup complete
- Will switch to latest version of distribution system over the next couple of weeks
- LV
- Distribution system design completed by LANL/UNM
- First production board expected this month, also real LV supplies
- DAQ
- Hookup to GTM, DCM, associated software completed by Ming, Jamie, Mickey
- ARCNet:
- Preamp, AMU/ADC, FPGA downloads available (Andrew). Also, board monitoring (T, I, V)
- Calibration System
- Already had gone through few rounds (Pat and Mike); final or nearly final system expected available for octant test