Timeline for Milestones |
|
July |
| Continue testing of modules
under direction of Ray. |
| Begin construction of stands |
|
August |
| Conclude testing of modules |
| Complete construction of
stands |
| Full Chain test of FEE |
| September |
| Stack modules on stand |
| Run cables to counting house |
|
October |
|
Ship modules to 1008, install. |
|
Connect cables and tie into DAQ |
| November |
| Calibrate and debug during
cool down |
| December |
| RHIC Run III starts. |
|
A copy of the current project file can be
found here.
This Week
- Conclude test of first stack of 40 modules.
Next Week
- Ship new stack of calorimeter modules to the high bay and begin
studies.
|