Minutes of the HEBT telephone meeting - Aug. 7, 1998 Attendants: BNL: Y.Goto, E.Kistenev, N.Saito, H.Torii, S.White, G.Young Muenster: D.Bucher * Position detector DWC, preamp, cables, L.V., etc. will be shipped from Muenster. Gas is already ordered at CERN. CFD's 5ch have to be shipped from BNL or found at the CERN electronics pool. LRS2228A (long range type) will be checked at ORNL stock. H.V. 3kV, 1microA, positive, 1ch is necessary. * Platform Muenster technician measured available width of the platform is 92cm. Width of the PbSc SM is 66cm, and that of PbGl 4SM's is 32 (or 48)cm. We can configure vertically PbSc and PbGl. It must be decided at CERN how to stack PbSc and PbGl (top or bottom). Height variation of the stage is 83cm. * Setup at the fence We plan to make our setup at the fence. Length of the SDM board cable is 20m. Where is the beam trigger logic made ? - Is it given, or do we make it by ourselves ? How is the timing ? Platform control and readout is not available at the fence ? * Equipments Dolly's with power supply and serial funout module should be confirmed at CERN. Transformer ( > 5kW)is found at CERN. * Shipping Aug.14 at BNL Receiving address is Tony Pryzybla, Expt.WA98/ALICE (E-mail: Tony@vxwa80.cern.ch) Bat 595 R-031, CERN PPE Division, Geneva CH-1211, Switzerland * Beam time plan PbGl people (Muenster) prefer to take energy sum data and 20degree non-orthogonal data. * Schedule Vanessa Mexner 8/23 - 9/? Henner Buesching about 1.5 week Stefan Bathe about 1.5 week Ullrich von Poblotzki about 1.5 week S.White 8/24 - 9/2 E.Kistenev 8/24 - 9/8 T.Awes 8/24 - ? Y.Goto 8/18 - 9/7 H.Torii 8/18 - 9/10 N.Saito 8/24 - 9/7 M.Ippolitov is staying all the time. Meeting at CERN - Aug.25 11AM at 2nd floor of Conf. Bldg. * Concerns Beam sharing between PHENIX/ALICE Platform - crane, align and survey works Platform - control and readout Beam trigger logic HIVOC