ID | Task Name | Duration | Start | Finish | Resource Names | % Complete |
1 | Finish North side | 145.75 days | Fri 3/15/02 | Fri 10/4/02 | | 65% |
2 | Sector EON | 132.5 days | Fri 3/15/02 | Tue 9/17/02 | | 39% |
3 | Disassemble Sector | 125.5 days | Fri 3/15/02 | Fri 9/6/02 | | 100% |
4 | Remove electronics | 0.8 days | Fri 3/15/02 | Fri 3/15/02 | | 100% |
5 | Remove P/s Boards | 0.5 days | Fri 3/15/02 | Fri 3/15/02 | Rob,Carter | 100% |
6 | Remove signal cables | 0.1 days | Fri 3/15/02 | Fri 3/15/02 | Rob,Carter | 100% |
7 | Remove LV cables | 0.05 days | Fri 3/15/02 | Fri 3/15/02 | Rob,Carter | 100% |
8 | Remove HV cables | 0.05 days | Fri 3/15/02 | Fri 3/15/02 | Rob,Carter | 100% |
9 | Move Gas manifold | 0.3 days | Tue 3/19/02 | Tue 3/19/02 | Carter | 100% |
10 | remove cable trays | 0.5 days | Wed 3/20/02 | Wed 3/20/02 | Rob,Xinhua | 100% |
11 | strip down tray | 0.3 days | Wed 3/20/02 | Wed 3/20/02 | Mark,Achim,Xinhua | 100% |
12 | Remove TRD ground straps | 0.5 days | Wed 3/20/02 | Wed 3/20/02 | Rob | 100% |
13 | open TR door | 0.5 days | Fri 9/6/02 | Fri 9/6/02 | Rob | 100% |
14 | Assemble Sector EON | 7 days | Fri 9/6/02 | Tue 9/17/02 | | 14% |
15 | insert TR | 1 day | Fri 9/6/02 | Mon 9/9/02 | Rob | 100% |
16 | HV test chambers | 0.25 days | Mon 9/9/02 | Mon 9/9/02 | | 0% |
17 | seal Doors | 0.5 days | Mon 9/9/02 | Tue 9/10/02 | | 0% |
18 | Attach TRD ground straps | 0.5 days | Tue 9/10/02 | Tue 9/10/02 | | 0% |
19 | Attach gas TRD manifold | 1 day | Tue 9/10/02 | Wed 9/11/02 | | 0% |
20 | attach cable tray | 1 day | Wed 9/11/02 | Thu 9/12/02 | | 0% |
21 | attach stand offs and align | 0.25 days | Thu 9/12/02 | Thu 9/12/02 | | 0% |
22 | attach gas manifold | 0.5 days | Fri 9/13/02 | Fri 9/13/02 | | 0% |
23 | run cables | 1 day | Fri 9/13/02 | Mon 9/16/02 | | 0% |
24 | replace electronics | 1 day | Mon 9/16/02 | Tue 9/17/02 | | 0% |
25 | | | | | | |
26 | Sector E1N | 131.75 days | Thu 4/4/02 | Fri 10/4/02 | | 73% |
27 | Disassemble certor | 113 days | Thu 4/4/02 | Mon 9/9/02 | | 100% |
28 | Remove electronics | 55.1 days | Thu 4/4/02 | Thu 6/20/02 | | 100% |
29 | Remove P/s Boards | 0.5 days | Thu 4/4/02 | Thu 4/4/02 | Mark,Xinhua | 100% |
30 | Remove signal cables | 0.1 days | Thu 6/20/02 | Thu 6/20/02 | Rob | 100% |
31 | Remove LV cables | 0.05 days | Thu 6/20/02 | Thu 6/20/02 | Rob | 100% |
32 | Remove HV cables | 0.05 days | Thu 6/20/02 | Thu 6/20/02 | Rob | 100% |
33 | Move Gas manifold | 0.3 days | Thu 6/20/02 | Thu 6/20/02 | Rob | 100% |
34 | remove cable trays | 0.5 days | Fri 6/21/02 | Fri 6/21/02 | Rob | 100% |
35 | Strip down tray | 0.3 days | Fri 6/21/02 | Fri 6/21/02 | Rob | 100% |
36 | Remove TRD ground straps | 0.5 days | Mon 9/9/02 | Mon 9/9/02 | Rob | 100% |
37 | open TR door | 0.5 days | Mon 9/9/02 | Mon 9/9/02 | Rob | 100% |
38 | Assemble Sector E1N | 18.75 days | Tue 9/10/02 | Fri 10/4/02 | | 64% |
39 | insert TR | 2 days | Tue 9/10/02 | Wed 9/11/02 | Rob | 100% |
40 | HV test chambers | 0.25 days | Thu 9/12/02 | Thu 9/12/02 | Rob | 100% |
41 | seal Doors | 1 day | Thu 9/12/02 | Fri 9/13/02 | Carter | 100% |
42 | Attach ground straps | 0.5 days | Mon 9/16/02 | Mon 9/16/02 | Rob | 100% |
43 | Attach gas TRD manifold | 0.5 days | Mon 9/16/02 | Tue 9/17/02 | Rob,Achim | 0% |
44 | attach cable tray | 1.5 days | Tue 9/17/02 | Tue 10/1/02 | John,bill | 100% |
45 | attach stand offs and align | 0.25 days | Wed 10/2/02 | Wed 10/2/02 | John,bill | 80% |
46 | attach gas manifold | 0.5 days | Wed 10/2/02 | Wed 10/2/02 | | 0% |
47 | run cables | 1 day | Wed 10/2/02 | Thu 10/3/02 | | 0% |
48 | replace electronics | 1 day | Thu 10/3/02 | Fri 10/4/02 | | 0% |
49 | | | | | | |
50 | Sector E2N | 24.25 days | Mon 4/29/02 | Fri 5/31/02 | | 72% |
51 | Disassemble Sector | 15 days | Mon 4/29/02 | Fri 5/17/02 | | 100% |
52 | Remove electronics | 0.5 days | Mon 4/29/02 | Mon 4/29/02 | | 100% |
53 | Remove P/s Boards | 0.5 days | Mon 4/29/02 | Mon 4/29/02 | Rob | 100% |
54 | Remove signal cables | 0.1 days | Mon 4/29/02 | Mon 4/29/02 | Rob | 100% |
55 | Remove LV cables | 0.05 days | Mon 4/29/02 | Mon 4/29/02 | Rob | 100% |
56 | Remove HV cables | 0.05 days | Mon 4/29/02 | Mon 4/29/02 | Rob | 100% |
57 | Move Gas manifold | 0.3 days | Mon 4/29/02 | Mon 4/29/02 | Rob | 100% |
58 | remove cable trays | 0.5 days | Mon 4/29/02 | Mon 4/29/02 | Rob,Carter | 100% |
59 | strip down tray | 0.3 days | Mon 4/29/02 | Tue 4/30/02 | Rob | 100% |
60 | Remove ground straps | 0.5 days | Tue 4/30/02 | Tue 4/30/02 | Rob | 100% |
61 | open TR door | 0.5 days | Fri 5/17/02 | Fri 5/17/02 | Rob,Carter | 100% |
62 | Assemble Sector E2N | 9.25 days | Mon 5/20/02 | Fri 5/31/02 | | 63% |
63 | insert TR | 2 days | Mon 5/20/02 | Tue 5/21/02 | Carter,Rob | 100% |
64 | HV test chambers | 0.25 days | Wed 5/22/02 | Wed 5/22/02 | Rob | 100% |
65 | seal Doors | 1 day | Thu 5/23/02 | Thu 5/23/02 | Carter,Rob | 100% |
66 | Attach ground straps | 0.5 days | Fri 5/24/02 | Fri 5/24/02 | Rob | 100% |
67 | Attach gas TRD manifold | 1.17 days | Fri 5/24/02 | Mon 5/27/02 | Carter,Rob,Achim | 43% |
68 | attach cable tray | 1 day | Mon 5/27/02 | Tue 5/28/02 | bill,John | 100% |
69 | attach stand offs and align | 0.25 days | Tue 5/28/02 | Tue 5/28/02 | John,bill | 85% |
70 | attach gas manifold | 0.5 days | Tue 5/28/02 | Wed 5/29/02 | | 0% |
71 | run cables | 1 day | Wed 5/29/02 | Thu 5/30/02 | | 0% |
72 | replace electronics | 1 day | Thu 5/30/02 | Fri 5/31/02 | | 0% |
73 | | | | | | |
74 | Sector E3N | 107.5 days | Fri 4/26/02 | Tue 9/24/02 | | 74% |
75 | Disassemble Sector | 98 days | Fri 4/26/02 | Tue 9/10/02 | | 100% |
76 | Remove electronics | 0.5 days | Fri 4/26/02 | Fri 4/26/02 | Carter | 100% |
77 | Remove P/s Boards | 0.5 days | Fri 4/26/02 | Fri 4/26/02 | Carter | 100% |
78 | Remove signal cables | 0.1 days | Fri 4/26/02 | Fri 4/26/02 | Carter | 100% |
79 | Remove LV cables | 0.05 days | Fri 4/26/02 | Fri 4/26/02 | Carter | 100% |
80 | Remove HV cables | 0.05 days | Fri 4/26/02 | Fri 4/26/02 | Carter | 100% |
81 | Move Gas manifold | 0.3 days | Fri 4/26/02 | Fri 4/26/02 | Carter | 100% |
82 | remove cable trays | 0.5 days | Mon 4/29/02 | Mon 4/29/02 | Carter | 100% |
83 | strip down tray | 0.3 days | Mon 4/29/02 | Mon 4/29/02 | Rob | 100% |
84 | Remove ground straps | 0.5 days | Tue 9/10/02 | Tue 9/10/02 | Rob,Carter | 100% |
85 | open TR door | 0.5 days | Tue 9/10/02 | Tue 9/10/02 | Rob,Carter | 100% |
86 | Assemble Sector E3N | 9.5 days | Wed 9/11/02 | Tue 9/24/02 | | 66% |
87 | insert TR | 2 days | Wed 9/11/02 | Thu 9/12/02 | Rob,Carter | 100% |
88 | HV test chambers | 0.2 days | Fri 9/13/02 | Fri 9/13/02 | Rob | 100% |
89 | seal Doors | 1 day | Mon 9/16/02 | Mon 9/16/02 | Carter | 100% |
90 | Attach ground straps | 0.5 days | Tue 9/17/02 | Tue 9/17/02 | Rob | 100% |
91 | Attach gas TRD manifold | 1 day | Tue 9/17/02 | Wed 9/18/02 | Carter,Rob | 50% |
92 | attach cable tray | 1 day | Wed 9/18/02 | Thu 9/19/02 | Rob,John | 100% |
93 | attach stand offs and align | 0.5 days | Thu 9/19/02 | Thu 9/19/02 | John,Rob | 100% |
94 | attach gas manifold | 0.5 days | Fri 9/20/02 | Fri 9/20/02 | | 0% |
95 | run cables | 1 day | Fri 9/20/02 | Mon 9/23/02 | | 0% |
96 | replace electronics | 1 day | Mon 9/23/02 | Tue 9/24/02 | | 0% |
97 | | | | | | |
98 | Finish Sorth side | 127 days | Mon 3/18/02 | Tue 9/10/02 | | 76% |
99 | Sector EOS | 65.5 days | Mon 3/18/02 | Mon 6/17/02 | | 70% |
100 | Disassemble Sector | 56 days | Mon 3/18/02 | Mon 6/3/02 | | 100% |
101 | Remove electronics | 0.5 days | Mon 3/18/02 | Mon 3/18/02 | | 100% |
102 | Remove P/s Boards | 0.5 days | Mon 3/18/02 | Mon 3/18/02 | Basanta,Xinhua | 100% |
103 | Remove signal cables | 0.1 days | Mon 3/18/02 | Mon 3/18/02 | Rob | 100% |
104 | Remove LV cables | 0.05 days | Mon 3/18/02 | Mon 3/18/02 | Rob | 100% |
105 | Remove HV cables | 0.05 days | Mon 3/18/02 | Mon 3/18/02 | Rob | 100% |
106 | Move Gas manifold | 0.3 days | Fri 3/22/02 | Fri 3/22/02 | Carter | 100% |
107 | remove cable trays | 0.5 days | Tue 4/9/02 | Tue 4/9/02 | Rob | 100% |
108 | strip down tray | 0.3 days | Fri 4/19/02 | Fri 4/19/02 | Rob | 100% |
109 | Remove TRD ground straps | 0.5 days | Mon 6/3/02 | Mon 6/3/02 | Rob | 100% |
110 | open TR door | 0.5 days | Mon 6/3/02 | Mon 6/3/02 | Rob,Carter | 100% |
111 | Assemble Sector EOS | 9.5 days | Tue 6/4/02 | Mon 6/17/02 | | 60% |
112 | attach cable tray | 1 day | Tue 6/4/02 | Tue 6/4/02 | | 100% |
113 | insert TR | 2 days | Wed 6/5/02 | Thu 6/6/02 | oliver,Carter | 100% |
114 | HV test chambers | 0.25 days | Fri 6/7/02 | Fri 6/7/02 | Rob | 100% |
115 | seal Doors | 1 day | Mon 6/10/02 | Mon 6/10/02 | Carter | 100% |
116 | Attach ground straps | 0.5 days | Tue 6/11/02 | Tue 6/11/02 | Rob | 100% |
117 | Attach gas TRD manifold | 1 day | Tue 6/11/02 | Wed 6/12/02 | Rob,Carter | 50% |
118 | attach stand offs and align | 0.5 days | Wed 6/12/02 | Wed 6/12/02 | | 0% |
119 | attach gas manifold | 0.5 days | Thu 6/13/02 | Thu 6/13/02 | | 0% |
120 | run cables | 1 day | Thu 6/13/02 | Fri 6/14/02 | | 0% |
121 | replace electronics | 1 day | Fri 6/14/02 | Mon 6/17/02 | | 0% |
122 | | | | | | |
123 | Sector E1S | 59.5 days | Thu 3/28/02 | Wed 6/19/02 | | 82% |
124 | Disassemble Sector | 52 days | Thu 3/28/02 | Fri 6/7/02 | | 100% |
125 | Remove electronics | 30.1 days | Thu 3/28/02 | Thu 5/9/02 | | 100% |
126 | Remove P/s Boards | 0.5 days | Thu 3/28/02 | Thu 3/28/02 | Mark,Xinhua | 100% |
127 | Remove signal cables | 0.1 days | Thu 3/28/02 | Thu 3/28/02 | Rob | 100% |
128 | Remove LV cables | 0.05 days | Thu 5/9/02 | Thu 5/9/02 | Rob | 100% |
129 | Remove HV cables | 0.05 days | Thu 5/9/02 | Thu 5/9/02 | Rob | 100% |
130 | Move Gas manifold | 0.3 days | Thu 5/9/02 | Thu 5/9/02 | Carter | 100% |
131 | remove cable trays | 0.5 days | Thu 5/9/02 | Thu 5/9/02 | Carter,Rob | 100% |
132 | strip down tray | 0.3 days | Thu 5/9/02 | Thu 5/9/02 | Rob | 100% |
133 | Remove ground straps | 0.5 days | Fri 6/7/02 | Fri 6/7/02 | Rob | 100% |
134 | open TR door | 0.5 days | Fri 6/7/02 | Fri 6/7/02 | Carter,Rob | 100% |
135 | Assemble Sector E1S | 7.5 days | Mon 6/10/02 | Wed 6/19/02 | | 76% |
136 | insert TR | 2 days | Mon 6/10/02 | Tue 6/11/02 | Carter,oliver | 100% |
137 | HV test chambers | 0.25 days | Mon 6/10/02 | Mon 6/10/02 | Rob | 100% |
138 | seal Doors | 1 day | Tue 6/11/02 | Tue 6/11/02 | Carter | 100% |
139 | Attach ground straps | 0.5 days | Wed 6/12/02 | Wed 6/12/02 | Rob | 100% |
140 | Attach gas TRD manifold | 1 day | Wed 6/12/02 | Thu 6/13/02 | Rob,oliver,Carter | 100% |
141 | attach cable tray | 1 day | Thu 6/13/02 | Fri 6/14/02 | John,Carter | 100% |
142 | attach stand offs and align | 0.5 days | Fri 6/14/02 | Fri 6/14/02 | Carter,Rob | 100% |
143 | attach gas manifold | 0.5 days | Mon 6/17/02 | Mon 6/17/02 | Carter | 80% |
144 | run cables | 1 day | Mon 6/17/02 | Tue 6/18/02 | | 0% |
145 | replace electronics | 1 day | Tue 6/18/02 | Wed 6/19/02 | | 0% |
146 | | | | | | |
147 | Sector E2S | 61.83 days | Wed 3/27/02 | Thu 6/20/02 | | 70% |
148 | Disassemble Sector | 53 days | Wed 3/27/02 | Fri 6/7/02 | | 100% |
149 | Remove electronics | 1 day | Wed 3/27/02 | Wed 3/27/02 | Carter,Rob | 100% |
150 | Remove P/s Boards | 1 day | Wed 3/27/02 | Wed 3/27/02 | Carter,Rob | 100% |
151 | Remove signal cables | 1 day | Wed 3/27/02 | Wed 3/27/02 | Carter,Rob | 100% |
152 | Remove LV cables | 1 day | Wed 3/27/02 | Wed 3/27/02 | Carter,Rob | 100% |
153 | Remove HV cables | 1 day | Wed 3/27/02 | Wed 3/27/02 | Carter,Rob | 100% |
154 | Move Gas manifold | 0.3 days | Thu 4/4/02 | Thu 4/4/02 | Carter,Rob | 100% |
155 | remove cable trays | 0.5 days | Thu 4/4/02 | Thu 4/4/02 | Carter,Rob | 100% |
156 | strip down tray | 0.3 days | Thu 4/4/02 | Fri 4/5/02 | Rob | 100% |
157 | Remove ground straps | 0.5 days | Fri 6/7/02 | Fri 6/7/02 | Rob | 100% |
158 | open TR door | 0.5 days | Fri 6/7/02 | Fri 6/7/02 | Carter | 100% |
159 | Assemble Sector E2S | 8.83 days | Mon 6/10/02 | Thu 6/20/02 | | 47% |
160 | insert TR | 1.33 days | Mon 6/10/02 | Tue 6/11/02 | Rob,Carter,oliver | 100% |
161 | HV test chambers | 0.25 days | Tue 6/11/02 | Tue 6/11/02 | Rob | 100% |
162 | seal Doors | 1 day | Wed 6/12/02 | Thu 6/13/02 | Rob | 80% |
163 | Attach ground straps | 0.5 days | Thu 6/13/02 | Thu 6/13/02 | Rob | 80% |
164 | Attach gas TRD manifold | 1 day | Thu 6/13/02 | Fri 6/14/02 | Rob,Carter | 50% |
165 | attach cable tray | 1 day | Fri 6/14/02 | Mon 6/17/02 | | 0% |
166 | attach stand offs and align | 0.5 days | Mon 6/17/02 | Tue 6/18/02 | | 0% |
167 | attach gas manifold | 0.5 days | Tue 6/18/02 | Tue 6/18/02 | | 0% |
168 | run cables | 1 day | Tue 6/18/02 | Wed 6/19/02 | Rob,bill | 50% |
169 | replace electronics | 1 day | Wed 6/19/02 | Thu 6/20/02 | | 0% |
170 | | | | | | |
171 | Sector E3S | 127 days | Mon 3/18/02 | Tue 9/10/02 | | 83% |
172 | Disassemble Sector | 17.85 days | Mon 3/18/02 | Wed 4/10/02 | | 100% |
173 | Remove electronics | 0.7 days | Mon 3/18/02 | Mon 3/18/02 | Rob,Carter | 100% |
174 | Remove P/s Boards | 0.5 days | Mon 3/18/02 | Mon 3/18/02 | Rob,Carter | 100% |
175 | Remove signal cables | 0.1 days | Mon 3/18/02 | Mon 3/18/02 | Rob,Carter | 100% |
176 | Remove LV cables | 0.05 days | Mon 3/18/02 | Mon 3/18/02 | Rob,Carter | 100% |
177 | Remove HV cables | 0.05 days | Mon 3/18/02 | Mon 3/18/02 | Rob,Carter | 100% |
178 | Move Gas manifold | 0.3 days | Tue 4/2/02 | Tue 4/2/02 | Carter | 100% |
179 | remove cable trays | 0.5 days | Tue 4/2/02 | Tue 4/2/02 | Rob,Carter | 100% |
180 | strip down tray | 0.3 days | Tue 4/2/02 | Tue 4/2/02 | Rob | 100% |
181 | Remove TRD ground straps | 0.5 days | Wed 4/10/02 | Wed 4/10/02 | Rob,Carter | 100% |
182 | open TR door | 0.5 days | Wed 4/10/02 | Wed 4/10/02 | Rob,Carter | 100% |
183 | Assemble Sector E3S | 109.15 days | Wed 4/10/02 | Tue 9/10/02 | | 77% |
184 | insert TR | 2 days | Wed 4/10/02 | Fri 4/12/02 | Rob,Carter | 100% |
185 | HV test chambers | 0.25 days | Fri 4/12/02 | Mon 4/15/02 | Rob | 100% |
186 | seal Doors | 1 day | Tue 8/27/02 | Tue 8/27/02 | Carter,oliver | 100% |
187 | Attach ground straps | 0.5 days | Thu 8/29/02 | Thu 8/29/02 | Rob,Carter | 100% |
188 | Attach gas TRD manifold | 0.75 days | Thu 8/29/02 | Fri 8/30/02 | oliver,Rob | 50% |
189 | attach cable tray | 1 day | Thu 9/5/02 | Thu 9/5/02 | Rob,Carter | 100% |
190 | attach stand offs and align | 0.5 days | Fri 9/6/02 | Fri 9/6/02 | Carter,Rob | 100% |
191 | attach gas manifold | 0.5 days | Fri 9/6/02 | Fri 9/6/02 | | 80% |
192 | run cables | 1 day | Mon 9/9/02 | Mon 9/9/02 | Rob,bill | 50% |
193 | replace electronics | 1 day | Tue 9/10/02 | Tue 9/10/02 | | 0% |
|