Forward Hadron Calorimeter

Archive Contacts Discuss Main Members Schedule

 

Timeline for Milestones
July
Continue testing of modules under direction of Ray.
Begin construction of stands
August
Conclude testing of modules
Complete construction of stands
Full Chain test of FEE
September
Stack modules on stand
Run cables to counting house
October
Ship modules to 1008, install.
Connect cables and tie into DAQ
November
Calibrate and debug during cool down
December
RHIC Run III starts.

 

A copy of the current project file can be found here.

 

This Week

  1. Conclude test of first stack of 40 modules.
 

Next Week

  1. Ship new stack of calorimeter modules to the high bay and begin studies.

 page contains a list of scheduled project events, and key milestones and



 For problems or questions regarding this web contact Stephen C. Johnson.
Last updated: 08/07/02.