Timeline for Milestones |
July |
Continue testing of modules
under direction of Ray. |
Begin construction of stands |
August |
Conclude testing of modules |
Complete construction of
stands |
Full Chain test of FEE |
September |
Stack modules on stand |
Run cables to counting house |
October |
Ship modules to 1008, install. |
Connect cables and tie into DAQ |
November |
Calibrate and debug during
cool down |
December |
RHIC Run III starts. |
|
A copy of the current project file can be
found here.
This Week
- Conclude test of first stack of 40 modules.
Next Week
- Ship new stack of calorimeter modules to the high bay and begin
studies.
|